Voltronic Power INFINISOLAR-WP-LV-15KW
The InfiniSolar WP LV InfiniSolar WP LV 15kw is a hybrid solar inverter rated InfiniSolar WP LV 15kw. Every figure on this page is read from the manufacturer's
Download PDF Datasheet WhatsApp UsTechnical Specifications
| Parameter | INFINISOLAR-WP-LV-15KW |
|---|---|
| PV String Input Data | |
| Max PV Input Power | 22000W |
| Max PV / DC Voltage | 120VDC/150 VDC 450 VDC |
| Electrical / AC Output Data | |
| Max Efficiency | 93% |
| Rated Apparent Power | 12000VA/12000W Default 15000VA/15000W MAX |
| Nominal Output Current | 26A +26A + 26A + 26A |
| Parallel Capability | Yes, 6 units |
| Phase | 120V/240V Split phase, 120V/208V Split phase |
| Max AC Input Current | 4/2+2+2+2 A |
| Pass-Through / Bypass Current | 200A |
| Battery Data | |
| Max Charge Current | 250A |
| Max Charge Power | 250A W |
| Protection Features | |
| AFCI / Arc Fault Protection | Yes |
| DC Switch | Yes |
| Grid Connection Standards | IEEE 1547.1:2020; IEEE 1547:2018 EMC FCC Part 15 |
| Ground Fault Monitoring | Yes |
| PV Rapid Shutdown | Yes |
| Safety / EMC Standards | UL1741SA, UL1741SB |
| Mechanical Data | |
| Weight | 65 kg |
Note: Specifications are based on the official Voltronic Power INFINISOLAR-WP-LV-15KW datasheet. Values may be subject to change; always verify against the latest manufacturer documentation before system design and procurement.
Availability & grid compliance in UAE
| Market | UAE |
| Grid authority / regulator | DEWA, ADDC, SEWA |
| Quotation currency | AED |
| Support hours timezone | Asia/Dubai |
| Delivery & installation coverage | Dubai, Abu Dhabi, Sharjah, Ajman, Ras Al Khaimah |
Figures on this page are the manufacturer's own, measured at the test conditions the datasheet states — they do not change by country. What changes is the approval that has to be met before the unit is energised: in UAE that is DEWA, ADDC, SEWA. Confirm the grid code, import requirements and any local certification with them, or with us, before you order.
Availability & grid compliance in Jordan
| Market | Jordan |
| Grid authority / regulator | EMRC Jordan |
| Quotation currency | JOD |
| Support hours timezone | Asia/Amman |
| Delivery & installation coverage | Amman, Zarqa, Irbid |
Figures on this page are the manufacturer's own, measured at the test conditions the datasheet states — they do not change by country. What changes is the approval that has to be met before the unit is energised: in Jordan that is EMRC Jordan. Confirm the grid code, import requirements and any local certification with them, or with us, before you order.